The construction of Ahmedbeyli-Fuzuli-Shusha highway with a lenght of 81,6 kilometers which connects liberated from occupation Fuzuli, Khojavend, Khojali and Shusha districts and originates from the M6 Hajigabul-Goradiz-Agbend-Zangezur corridor, continues at a rapid pace, according to the State Agency of Azerbaijan Automobile Roads.

Ahmedbeyli-Fuzuli-Shusha highway is being built with 4-6 lanes in accordance with the I technical degree.

Some 137 drainage channels are being laid on the territory, 30 underground crossings, seven road bridges, seven tunnels are being built, as well as nine viaducts.

Construction work on tunnels T4, T5 and T6 are already in the final stage. So, earthworks, laying of concrete, laying of drainage and cable pipes have been completed. Currently, work is being carried out on laying asphalt concrete pavement inside the tunnels, as well as at the entrances and exits.

Excavation and concrete works have also been completed in tunnels T1, T2 and T3. Work continues on laying cable pipes, concreting, etc.

The construction of road bridges, underpasses, round culverts and rectangular monolithic pipes continues. The total percentage of work performed on artificial structures of the facility has surpassed 70%.

Excavation work is also continuing along the road. Thus, according to the project, work continues on the expansion of the road, the construction of a new roadbed, as well as the construction of a road foundation using a sand-gravel mixture. Asphalting works have begun on the sections where the road base is ready.

In addition, work is being carried out on the construction of a road junction on the connecting section of the Victory Road with the Ahmedbeyli-Fuzuli-Shusha highway.

Photo by Azerbaijan's State Agency of Automobile Roads