CPC to launch Kropotkin Pump Station into operation in May

The Caspian Pipeline Consortium

The Caspian Pipeline Consortium (CPC) plans to return into operation the Kropotkin Pump Station damaged earlier by Ukrainian drones after May 20, CEO Nikolay Gorban said, cited on the CPC’s Telegram channel.

According to him, construction and installation work has been completed to date in full scope. Transformers were restored; the gas turbine unit and the generator were restored, tested and put into service, Gorban noted.

The main switchgear building was restored, the rack was restored; wiring inside cabinets and testing of signals are close to completion, the chief executive said.

"The CPC also takes note of a certain decline in pumping over its system but it is premature so far to forecast transportation volumes as of the end of the entire 2025," Nikolay Gorban said.