Laying another Nord Stream 2 line to begin in late March

Laying another Nord Stream 2 line to begin in late March

Work on laying the second line of the Nord Stream 2 gas pipeline in the exclusive economic zone of Denmark will begin at the end of March, according to the schedule of the Nord Stream 2 AG company, provided by the Danish Energy Agency.

"Construction schedule Line A. … Based on the successful completion of the Sea Trials and Preproduction Trials planned to start from mid-March. It is envisaged that pipelay will resume in late March and continue through to late Q3 2021," TASS cited the statement as saying.