TAP project 88.8% completed

TAP project 88.8% completed

The Trans Adriatic Pipeline (TAP) project is 88.8% completed as of late July 2019, according to the updated data published on the website of TAP AG consortium.

"TAP is currently moving further into the project construction phase. Every day hundreds of meters of TAP’s Right of Way (ROW) are cleared, strung, welded, lowered into the trenches and backfilled, in line with the project construction steps and schedule," the message reads.

The completeness percentage includes all engineering and procurement scope as well as the progress on the 12 pipeline construction steps onshore, the construction of above ground installations (block valve stations, compressor stations and pipeline receiving terminal) as well as offshore construction and pipeline installation.

TAP project, worth 4.5 billion euros, is one of the priority energy projects for the European Union. The project envisages transportation of gas from Azerbaijan's Shah Deniz Stage 2 to the EU countries.