Railway traffic to the stations of Novorossiysk, Grushevaya, Vyshestebliyevskaya has been restored, Yuga.ru reports.
The bridge on the 363rd km of the Krymskaya-Bakanskaya line in Novorossiysk was opened on July 10 for 7 cargo trains. 15 trains were planned for July 11, about 50% of average. 3 trains were sent to Grushevaya on July 10-11, one to Vyshestebliyevskaya.
17 trains (about 1000 carriages) plan to move to Novorossiysk, 300 carriages to Bataysk and Krasnodar-Sortirovochny. 9 trains plan to arrive in Grushevaya and Vyshestebliyevskaya.
Flood caused delays in railway traffic. Over 2,000 workers were mobilized. Work was organized at 15 blocks. Over 15 km of railways were fixed and cleared.