IDGC of North Caucasus finds 5,000 potential clients in Jan-Jun 2012

IDGC of North Caucasus finds 5,000 potential clients in Jan-Jun 2012

The Interregional Distribution Grid Company (IDGC) of the North Caucasus, Dagenergoset and Nurenergo (Chechnya) have received applications from 4,860 people willing to become their clients in January-June 2012. Together they will need 372 MW. 32 applications arrived from major consumers that need over 750 KW.

4,200 deals with a power of 53.7 MW were realized in the first half of 2012. Income from connecting them totalled 52.9 million rubles.

Some of the biggest projects are the oil pumping stations of the Kaspiyskiy Truboprovodny Consortium OPS-4 and OPS-5 and the Chiryurtskaya Dam.

The Gotsatlinskaya Dam in Dagestan is one of the most promising projects